A negative cost variance combined with a negative schedule variance is an indicator of

Respuesta :

Kalahira
Kalahira Kalahira
  • 27-11-2017
Cost variance and schedule variance are indicators of efficiency of a project. Therefore if you have a negative cost variance and a negative schedule variance, then the project is inefficient and you should look into ways to cut costs and save money.
Answer Link

Otras preguntas

to rent office space for your business, you must pay a one time fee of $1000 and pay rent of $800 per month.A. Write a linear model that represents the total co
What is the sum of the first 75 even numbers starting with 2? Enter your answer in the box.
Congressional Reconstruction is characterized by which of the following? A. race riots throughout many northern cities B. declaration of martial law in so
Read the passage from Animal Farm. Rumours of a wonderful farm, where the human beings had been turned out and the animals managed their own affairs, continued
PLEASE HELP ME!!!!!!!!!!!!!!!!!!!!
If (x)=x^2+2x-5. What is f(a+1)
What substance cannot be broken down by chemical change
A textbook costs 65.49 before tax the tax on the textbook is 6.5% what is the cost of the text book
What is the volume of a cylinder with 14 ft and 9ft
15,700 to nearest thousand