Respuesta :
Answer:
42 add'lmen required
Step-by-step explanation:
12 men x 27 days = 324 man-days required to complete the project
324 man-days / x men = 6 days
x = 54 men required to complete in 6 days ....or 42 add'l men required
Answer:
42 add'lmen required
Step-by-step explanation:
12 men x 27 days = 324 man-days required to complete the project
324 man-days / x men = 6 days
x = 54 men required to complete in 6 days ....or 42 add'l men required