a company planned to finish a project with 80 people in 80 days.if after the initial 10 days,the number of people reduces to 70,by how many days will the project get delayed?​

Respuesta :

Аноним Аноним
  • 17-10-2021

Answer:

10 days delay

Step-by-step explanation:

in ten day 12.5% work done by 80 peoples

then 87.5% work hsas to be done by 70 peoples

the days consoder as 'x'

then( 70/x)*100 = 87.5

1/x = 87.5/7000

x =7000/87.5

x =80

so 70 peoples take 80 days to finish the work

so 10 days delay

Answer Link

Otras preguntas

What compound makes up carbohydrates?
Solve each problem by using the quadratic formula. Write solutions in simplest radical form. 2x2 + 2x – 2 = 0
The sides of a triangle are x , x +1 , 2 x -1 and its area is x root of 10 .Find the value of x.
One goal of the Congress of Vienna was to (1) establish a new balance of power in Europe (2) protect Europe from Ottoman advances (3) end abuses within the
How did the Swahili language develop?
Who was Benjamin Franklin?
What were three developments in the arts during the Enlightenment?
How many European countries held African colonies by 1914?
Laura and Brent paddled a canoe 6 miles upstream in four hours. The return trip took three hours. Find the rate at which Laura and Brent paddled the canoe is st
What was the purpose of the League of Nations?